In this article, we highlight planned HEB grocery stores in Texas, and even offer insight into projects that are already underway. Additionally, we include residential data for the areas surrounding the planned HEB grocery store sites. As you can see from the below Geospex screenshot, planned HEB Grocery store construction is concentrated in and around Texas’s major cities: Austin, Dallas, Houston, and San Antonio.

Geospex screenshot of 58 HEB Grocery stores in planning and under construction in Texas

While such a trend is typical because of the foot traffic that a grocery store can expect in urban hubs, the residential areas that these planned HEB Grocery stores will serve are of note. As such, we’ve included both multi- and single-family residential data within a 20-minute drive of each future HEB Grocery location, courtesy of BuildCentral’s MultiFamilyData,  SingleFamilyData and Planned Grocery. 

This list is based on projects from Planned Grocery and BuildCentral’s ConstructionWire, per a query for HEB Grocery stores in planning and under construction in Texas. The projects are sorted by greater metropolitan area. Each city features both a HEB Grocery in planning and one that is already under construction.  

Austin 

HEB Grocery Velocity Crossings 

Planned Grocery screenshot of residential data within 20-minute drive of the HEB Velocity Crossings project

Project Type/Size:  Retail/Grocery (50,000-99,999 sq-ft) 
Construction Type:  New 
Estimated Value:  $5-$25 million 
Sector:  Private 
Location:  Austin, TX 78617. Intersection of Texas Highway 71 and 130 
Details:  Plans call for construction of an H-E-B grocery store as part of the Velocity Crossings development. 
Stage:  Planning (Active) 
Construction End:  N/A 
Bid Due Date:  N/A 

 

HEB Grocery Lake Austin 

Planned Grocery screenshot of residential data within 20-minute drie of the HEB Lake Austin project

Project Type/Size:  Retail/Restaurants/Grocery (110,000 sq-ft), Parking Structures 
Construction Type:  New 
Estimated Value:  $5-$25 million 
Sector:  Private 
Location:  Austin, TX 78703. 715 Exposition Blvd 
Details:  Plans call for the construction of a multi-level 110,000-square-foot HEB store that will include underground parking and a True Texas BBQ (HEB’s in-house restaurant). 
Stage:  Early Construction 
Construction Start:  Q3/2021 
Construction End:  Q3/2022 
Bid Due Date:  N/A 

 

Dallas 

HEB Grocery Murphy 

Planned Grocery screenshot of residential data within 20-minute drive of the HEB Murphy project

Project Type/Size:  Retail/Grocery (50,000-99,999 sq-ft) 
Construction Type:  New 
Estimated Value:  $5-$25 million 
Sector:  Private 
Location:  Murphy, TX 75098. Intersection of FM 544 and McCreary Rd. 
Details:  Plans call for the construction of a new HEB grocery store in the McCreary Marketplace. 
Stage:  Planning (Active) 
Construction End:  N/A 
Bid Due Date:  N/A 

 

HEB Grocery Plano 

Planned Grocery screenshot of residential data within 20-minute drive of the HEB Plano project

Project Type/Size:  Retail/Grocery (110,000 sq-ft) 
Construction Type:  New 
Estimated Value:  $5-$25 million 
Sector:  Private 
Location:  Plano, TX 75024. SWC Preston Road and Spring Creek Parkway 
Details:  Plans call for the construction of a 110,000 square-foot H-E-B grocery store. 
Stage:  Early Construction 
Construction Start:  Q3/2021 
Construction End:  Q4/2022 
Bid Due Date:  N/A 

 

Houston 

HEB Grocery Mixed-Use Building 

Planned Grocery screenshot of residential data within 20-minute drive of the HEB Mixed-Use project

Project Type/Size:  MultiFamily (151-250 units), Retail/Grocery (10,000-24,999 sq-ft) 
Construction Type:  New 
Estimated Value:  $5-$25 million 
Sector:  Private 
Location:  Houston, TX 77098. 2612 West Alabama Street 
Details:  Plans call for new construction of a mixed-use building anchored by an HEB Grocery store, and consisting of a large number of apartment units. 
Stage:  Planning (Active) 
Construction End:  N/A 
Bid Due Date:  N/A 

HEB Grocery Eastfield at Baybrook 

Planned Grocery screenshot of residential data within 20-minute drive of the Eastfield at Baybrook project

Project Type/Size:  Retail (30,000 sq-ft), Grocery (105,260 sq-ft) 
Construction Type:  New 
Estimated Value:  $25-$100 million 
Sector:  Private 
Location:  Houston, TX 77204. SEC I-45 & El Dorado Blvd. 
Details:  Plans call for the construction of a 105,000-square-foot HEB Grocery store and 30,000 square feet of multi-tenant retail buildings. 
Stage:  Construction 
Construction Start:  Q2/2021 
Construction End:  Q2/2022 
Bid Due Date:  N/A 

 

San Antonio 

HEB Grocery San Antonio 

Planned Grocery screenshot of residential data within 20-minute drive of the HEB San Antonio project

Project Type/Size:  Retail/Grocery (50,000-99,999 sq-ft) 
Construction Type:  New 
Estimated Value:  $5-$25 million 
Sector:  Private 
Location:  San Antonio, TX 78251. NE of Hunt Ln & Potranco Rd 
Details:  Plans call for the construction of a HEB supermarket. 
Stage:  Planning (Active) 
Construction End:  N/A 
Bid Due Date:  N/A 

HEB Grocery Cibolo 

Planned Grocery screenshot of residential data within 20-minute drive of the HEB Cibolo project

Project Type/Size:  Retail/Grocery (112,747 sq-ft) 
Construction Type:  New 
Estimated Value:  $38 million 
Sector:  Private 
Location:  Cibolo, TX 78108. 850 F.M. 1103 
Details:  Plans call for the construction of a 112,747-square-foot HEB grocery store. 
Stage:  Groundbreaking 
Construction Start:  Q4/2021 
Construction End:  Q2/2023 
Bid Due Date:  N/A 

Keep in mind that this list represents just a sampling of planned HEB Grocery construction. In all, BuildCentral is currently keeping tabs on 58 HEB Grocery stores either in planning or under construction across Texas. 

Was this blog helpful? 

Subscribe to the BuildCentral Newsletter to receive promos, feature updates, early project insights, growth tips and more. Published twice a month, we help you stay current on industry news, sales & marketing best practices and insights into top new projects and key players. 

Request a free trial today to learn more about BCI|BuildCentral’s products, and to start tracking everything from warehouse and industrial projects to retail, hotel, medical, CRE, multi-family, and mixed-use developments.